A production hall and office building in Gliwice

Go back

Building type

A production hall and office building in Gliwice.

Description

A production hall for the company assembling battery systems.

The facility consists of the production hall building, the staff and office building, MV switchgear room, carports, car parks, roads and manoeuvring yards for trucks.

Dimensions

  • Usable area of the production hall: 5 375 m2
  • Usable area of the office building: 4 804 m2
  • Volume of the production hall: 53 197 m3
  • Volume of the office building: 23 604 m3

Construction

The project completed in July 2017.

BMZ stage 2 – construction status at 31/01/2019

Construction status [31.01.2019] Currently, works are being carried out in the area of ​​the indirect foundation of the “D” segment – Warehouse. The General Contractor mainly carries out works related to the ground foundation piles.

Read more

BMZ2 – completion of design works

The end of the project! Completion of works related to the releasing a final project for the extension of an industrial plant at ul. Albert Einstein 9 in Gliwice for the company BMZ Poland. Already with a building permit!

Read more